Bathroom renovation costs: build a complete budget
A bathroom budget needs more than the suite price. Separate products, installation, preparation and work outside the room, then record what each written quote includes.

How much will your bathroom renovation cost?
There is no reliable single price for an unspecified bathroom. Room size, layout changes, product choices, existing conditions and location all affect what needs pricing. A replacement within the existing layout and a new wet room are different briefs. Use an early estimate as a planning range, then obtain site-specific written quotations.
Write down whether you are keeping the bath, shower, basin and WC positions. Identify the exact products you want and who supplies them. Ask the installer to identify any assumptions about concealed conditions, access and preparation before treating a total as complete.
Printable bathroom budget checklist
Print this page or save it as a PDF from your browser. Mark every row “included”, “separate” or “not confirmed”. Keep the same tax basis and quote revision across all amounts. Unknown does not mean zero.
| Item | What to confirm | Status / price / reference |
|---|---|---|
| Suite and fittings | Exact bath, shower, WC, basin, taps, screens and furniture; delivery and accessories. | ________________ |
| Removal and protection | Strip-out, waste disposal, protection and making good outside the room. | ________________ |
| Plumbing and drainage | Connections, any relocation, testing and exclusions to be confirmed by the installer. | ________________ |
| Preparation | Floor and wall condition, substrates and the proposed waterproofing specification. | ________________ |
| Electrical and ventilation | Lighting, extraction, heating and any associated work or certification identified by suitable professionals. | ________________ |
| Finishes and labour | Tiling areas, tile supply, trims, adhesives, fitting, decorating and final sealing. | ________________ |
| Practical costs | Access, temporary arrangements, design fees and separately priced work. | ________________ |
| Tax and contingency | Tax included/excluded; a separate reserve for uncertainty, not another contractor charge. | ________________ |
Avoid counting an allowance twice
Fictional arithmetic, not market prices: an £8,000 installation offer already includes a £1,000 tile allowance. Replacing that allowance with a confirmed £1,400 tile selection adds £400, not £1,400, if everything else remains unchanged. Ask for a revised quote: different tiles may also change fitting work.
A separate £500 vanity excluded from that offer would bring the example total to £8,900. Any unpriced work must still be listed as unknown. See the renovation budget planner for keeping quoted work and contingency separate.
Questions for your installer
- Are all suppliers and installers pricing the same layout and product list?
- Which concealed conditions could change the price, and how will changes be agreed?
- Who supplies small fittings, collects deliveries and deals with damaged products?
- What are the payment stages, expected programme, quote validity and arrangements for defects?
- What technical checks and approvals need confirming for this property?
This is a budget checklist, not installation or regulatory advice. Have project-specific safety, design and compliance assessed by appropriate professionals. Use our quote comparison worksheet to keep exclusions visible.