Quote terms explained
What are preliminaries on a building quote?
Preliminaries, or prelims, are the costs of running the site rather than building anything: site setup, scaffolding, skips, site welfare (a toilet and somewhere for the workers to wash and eat), supervision, insurance, small plant, protection and cleaning. Estimators typically put them at 5 to 15% of the building cost, about 10% on a typical job. Some builders list them as a line, some spread them through their prices, and some leave parts of them out. Our typical price for a 25 m² single storey extension, £63,500 to £78,000 including VAT outside London (Estiquote cost model, prices reviewed 25 September 2026), already allows for the preliminaries: site setup, scaffold, skips, welfare (toilets and a rest area for the workers), supervision and insurance.
Already have a quote? Check it with the free quote checker against the typical price for the same job where you live.
What prelims usually cover
| Item | Typical price before VAT | Notes |
|---|---|---|
| Scaffolding, one elevation | £450 to £800 for 6 to 8 weeks | A single storey often needs less |
| 8-yard skip | £240 to £360 each | A road permit is extra; London costs more |
| Site welfare | £15 to £150 a week | A serviced toilet at the low end, a welfare cabin at the top |
| All the preliminaries together: the items above, plus supervision, insurance, small plant, protection and cleaning | 5 to 15% of the net building cost | About 10% on a typical job; higher in London. This is the whole of the preliminaries, not an amount on top of the lines above |
Ranges from the Estiquote unit rate book (September 2026), drawn from Checkatrade, MyJobQuote, GigLoo and published builder guidance. Every rate and its source is in our published rate book.
Why prelims trip up quote comparisons
One builder shows prelims as a separate line. Another shows none, because the cost is spread through the other sections. A third genuinely leaves out scaffolding and skips, which you will pay for later. All three totals look different for reasons that have nothing to do with value. Ask each builder: "Are scaffolding, skips, welfare and supervision included, and where?"
Next
Read what a builder's quote should include, and check your total with the free quote checker.
Check your quote
Type the builder’s total into the free quote checker, say what it includes, and see whether it sits below, within or above the typical price for that job in your area. Your quote and postcode stay on your phone or computer.