Why are my builder quotes so different?
Quotes for the same extension often differ by tens of thousands of pounds because the builders are not really pricing the same job. They read the drawings differently, leave out different items, treat VAT differently and put a different price on risk. The finish alone moves a 25 m² single-storey rear extension from £51,500 at the low end of a basic finish to £99,000 at the top of a premium one, including VAT outside London (Estiquote cost model, prices reviewed 25 September 2026). Once you line them up like for like, honest quotes usually land much closer together.
Already have a quote? Check it with the free quote checker against the typical price for the same job where you live.
The seven usual reasons
- Different scope. One quote includes the kitchen, electrics, plumbing, flooring and decorating. Another stops at plastered walls and leaves the rest to you.
- Provisional sums. A provisional sum is a placeholder for work the builder cannot price yet, such as foundations or drainage. A quote full of low provisional sums looks cheap and grows once work starts.
- VAT. Most building work carries VAT at 20%. Ask each builder to confirm whether their price includes it. Some quotes add it on top, some include it, and builders below the VAT registration threshold do not charge it at all.
- Construction type. A lightweight glazed room or conservatory costs far less than an insulated extension built to Building Regulations, but it is not the same thing. It may not be comfortable all year, and buyers and lenders can treat it differently.
- Groundwork assumptions. Foundations, drains and tree roots stay hidden until digging starts. One builder allows for deeper foundations; another assumes the minimum and charges extra later.
- Preliminaries. Site setup, scaffolding, skips, welfare (toilets and a rest area for the workers), supervision and insurance. Some builders list them, some spread them through their rates, and some leave them out.
- Workload and risk. Busy builders price high because they do not need the job. Others price low to win it and recover the difference through extras.
Finish level alone moves the price a long way
The same 25 m² single-storey rear extension costs very different amounts depending on the specification. If one builder has priced basic doors, windows and finishes and another has priced large sliding doors and premium flooring, their quotes will be far apart and both can be fair.
| Finish | Building work | Per m² |
|---|---|---|
| Basic | £51,500 to £63,000 | £2,100 to £2,500 |
| Mid-range | £63,500 to £78,000 | £2,500 to £3,100 |
| Premium | £81,500 to £99,000 | £3,300 to £4,000 |
How to make quotes comparable
- Send every builder the same drawings and the same written specification.
- Ask for an itemised price rather than a single figure.
- List every exclusion and provisional sum side by side.
- Add an item a quote leaves out only when you have a credible price for it; otherwise ask that builder to price it.
- Convert every quote to a price including VAT.
- Compare the results with the budget range for your size, finish and region with the quote checker.
Our free quote comparison worksheet takes you through this line by line.
When a low quote is a warning
- It is far below the others and you cannot see why
- Much of the price sits in provisional sums
- There is no mention of building control or structural calculations
- The builder wants cash, or a large payment before work starts
- There is no written specification, contract or guarantee
A low quote is not automatically a bad one, but it should be explained. Ask the builder to confirm in writing what is included.
In Scotland some of this works differently. You need a building warrant from your council before work starts (mygov.scot), in place of building control approval. When the work is finished, you or your agent submit the completion certificate to the council, which accepts it once it is satisfied. Where this guide says to wait for the completion certificate, wait for that acceptance. The Party Wall etc. Act 1996 doesn’t apply, so there are no party wall notices or surveyors. See extension costs and rules in Scotland.